Hopsrig 1

Hopsrig

Dumfries & Galloway

In Development

The proposed Hopsrig Wind Farm is located off the B709, approximately 7.5 km northwest of Langholm and 15 km northeast of Lockerbie in Dumfries & Galloway on an area of existing commercial forestry plantation. 

This proposal has been revised, Additional Information was submitted to the Energy Consents Unit, reflecting a new 12 turbine layout, with a maximum tip height of 200 m giving a total installed capacity of approximately 79.2 MW. This layout reflects the comments received on landscape where one turbine has been removed and a further 3 have been relocated to set them back from the Esk Valley landscape.

To show your support for the project, get involved

Get Involved
turbine icon

12

Turbines

height icon

200 m

Maximum Tip Height

generating icon

79 MW

Generating Capacity

carbon icon

99,723

Tonnes of CO2 saved each year

supplies icon

72,614

Homes Powered

Location: Dumfries & Galloway

January 2019

Hopsrig was granted consent by Dumfries and Galloway Council for 12 turbines at 140 m to tip

November 2021

Section 36 application submitted to Energy Consents for an optimised site layout comprising 13 turbines at 200 m to tip

August 2022

Additional Environmental Information was submitted with respect to traffic and transport, and noise, providing an updated assessment

February 2024

Additional Environmental Information was submitted to ECU to reflect a new layout for 12 turbines at 200 m to tip

August 2024

Dumfries & Galloway Planning Application Committee

Late 2024

Decision from the Scottish Ministers is expected to be issued

2025

Preparation for construction of the wind farm

2027

Wind farm expected to be ready to connect to the national grid.

Following positive engagement with key stakeholders, we have submitted Additional Information to the Energy Consents Unit in February 2024 reflecting changes to site design following the consultation process. The optimised sites continue to bring greater associated community and environmental benefits.

Kirstin Leckie, Senior Project Manager

Commitment to Communities

If built, Hopsrig Wind Farm will offer an industry-leading community investment rate of £7,000 annually per megawatt of installed wind capacity. That figure would return approximately £553,000 per year to communities surrounding the wind farm.

Shared Ownership

In addition to these community investment funds, Muirhall Energy will offer up to 10% community shared ownership in Hopsrig Wind Farm. Conversations have already taken place with communities around the proposed development and the dialogue will continue as the project progresses.  

Should Hopsrig wind farm be consented, an Initial Investment fund (IIF) would be set up to support communities when construction begins

Our commitment to the local communities continues with the revised Hopsrig scheme where shared ownership will once again be offered. 

Kirstin Leckie, Senior Project Manager

All application documents and public advertisements are available for viewing and download through the DropBox link below. 

Project Documents

Access Link