Loganhead has consent for 8 turbines at 135 m to tip . In November 2021,a section 36 application was submitted to the Energy Consents Unit for anoptimised scheme for the site, within the same development footprint. Theapplication was submitted for 9 turbines at 200 m to tip, which will generate asubstantially greater amount of energy, bringing with it greater environmentaland community benefits.
In August 2022, Additional Environmental Information was submitted withrespect to traffic and transport, and noise, providing an updated chapter foreach.
In March 2023, an updated planningstatement document was submitted to support the application following theadoption of the National Planning Framework 4.
Following consultation and stakeholder responses, Additional Environmental Information has been submitted in February 2024 to reflect a new 8 turbine layout, with a maximum tip height of200 m giving a total indicative installed capacity of 53 MW, and all its associated infrastructure.
If you feel you can support the project, you can do so by writing to the Energy Consents Unit using reference ECU00002161. Email: representations@gov.scot
Post: Energy Consents Unit, 5 Atlantic Quay, Broomielaw, Glasgow, G2 8LU.
Kirstin Leckie, Project Manager
If built, Loganhead Wind Farm will offer an industry-leading community investment rate of £7,000 annually per megawatt of installed wind capacity. That figure would return approximately £415,000 per year to communities surrounding the wind farm.
In addition to these community investment funds, Muirhall Energy will offer up to 10% community shared ownership in Loganhead Wind Farm. Conversations have already taken place with communities around the proposed development and the dialogue will continue as the project progresses.
Should Loganhead Wind Farm be consented, an Initial Investment fund (IIF) would be set up to support communities when construction begins.
The development at Loganhead also offers an opportunity for the local community to own up to 10% of the wind farm following the model of our landmark Community Ownership Scheme at Crossdykes wind farm.
Shared ownership would generate considerable extra income to the local area, over and above the community investment funding which is a commitment made regardless of whether the shared ownership option is taken up. You can read more about shared ownership here.
This offer was taken up by numerous community councils from the area surrounding Crossdykes, which will benefit the local area with increased investment in the community for years to come.
Chris Miles, Chair of Dumfriesshire East Community Benefit Group (on the shared ownership of Crossdykes wind farm).
The wind farm was consented by Dumfries and Galloway Council in 2019.
A Section 36 application will be submitted to the Scottish Government Energy Consents Unit in November 2021, for an expanded wind farm with larger turbines and more energy and financial potential.
Consented = 8 turbines of approximately 3.2 MW each.
Total Capacity = 25.6 MW
Revised application = 9 turbines of approximately 6 MW each.
Total Capacity = 59 MW
Consented height to blade tip = 135m
Revised application height to blade tip = 200m